Abstract
The investigators found no fault with the company's SOPs but said that "insufficient planning and lead-time was allowed for the clearance team to be prepared…". They thought that the "contractual pressure created an atmosphere of unnecessary urgency", that communications between the demining company and the [QA] were inadequate and that the parties involved were all interpreting the contract differently.