The deminer was investigating the signal and excavating by sitting/squatting position and his prodder/bayonet detonated the PMN mine. The evidence on site shows that the excavation of the signal started from the first mark, and not 30cm back from the indication. The bayonet directly touched the mine causing a detonation. This indicates he was not conducting operations with the correct procedure.